Back to projects

Ultraviolet (UV) Disinfection at Durham Wastewater Treatment Plant

West Grey, Ontario

completeWastewaterCWWF
Federal contribution
$97,104
Federal share37%

of $265.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of West Grey
Construction start
Oct 31, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017