Rehabilitation of County Road 25

Prince Edward County, Ontario

completeHighways and RoadsISF
Federal contribution
$195,948
Federal share25%

of $770.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Prince Edward
Construction start
May 3, 2010(actual)
Construction end
Sep 20, 2010(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Aug 30, 2010