County Road 3 Rehabilitation

Prince Edward County, Ontario

completeHighways and RoadsSCF
Federal contribution
$3.1M
$3,120,640
Federal share33%

of $9.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2015
201620172018201920202021
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 2, 2016(actual)
Construction end
Dec 21, 2020(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 11, 2016
  • Construction end3 months earlyforecast Mar 31, 2021

Also in Prince Edward County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46229 in the federal list. How to read these figures.