Lionhead Pumping Station, Decommissioning and Gravity Sewer Connection
Federal contribution
$381,457
Federal share31%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Feb 24, 2010(actual)
- Construction end
- Mar 18, 2011(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Mar 31, 2010
Also in Brampton
- Transit Maintenance & Storage Facility$69.9M
- Protecting our future: Flood mitigation and physical, economic, social and cultural resilience for historic downtown Brampton, on by reconstructing 600M of the concrete Etobicoke Creek bypass channel$38.9M
- 2023 Replacement Buses$25.5M
- 2020-2024 Bus Refurbishments$22.2M
- 2020 Growth Buses$18.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32438 in the federal list. How to read these figures.