Watermain Construction on Anne Street, Cundles Road, Kozlov Street and Heather Street

Barrie, Ontario

completeDrinking WaterISF
Federal contribution
$992,700
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Barrie
Construction start
Apr 12, 2010(actual)
Construction end
Aug 18, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 15, 2009
  • Construction end6 weeks earlyforecast Sep 30, 2010