Back to projects

Walker Road Reconstruction

Windsor, Ontario

completeHighways and RoadsISF
Federal contribution
$3.5M
$3,488,295
Federal share29%

of $11.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Windsor
Construction start
Mar 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011