Walker/Wyandotte intersection improvements
Federal contribution
$832,889
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Dec 31, 2009
- Construction end3 months earlyforecast Dec 31, 2010
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32656 in the federal list. How to read these figures.