Jackson Park Renewal
Federal contribution
$266,667
Federal share33%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Nov 30, 2009(actual)
- Construction end
- Aug 17, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 8, 2009
- Construction end2 months earlyforecast Oct 31, 2011