Central Riverfront Festival Plaza

Windsor, Ontario

completeRecreationISF
Federal contribution
$666,667
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Windsor
Construction start
Jun 22, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 31, 2010
  • Construction end2 weeks lateforecast Oct 15, 2011