Ganatchio Trail Reconstruction

Windsor, Ontario

completeActive TransportationISF
Federal contribution
$200,000
Federal share33%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Windsor
Construction start
Nov 1, 2009(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2009
  • Construction end2 weeks lateforecast Sep 30, 2010