City Centre Streetscape

Windsor, Ontario

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,409,168
Federal share20%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Windsor
Construction start
Mar 29, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Mar 15, 2010
  • Construction end4 weeks lateforecast Feb 28, 2011

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32686 in the federal list. How to read these figures.