Telus World of Science
Federal contribution
$40.0M
$40,000,000
Federal share48%
of $84.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 5, 2009
20092010201120122013
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Calgary Science Centre and Creative Kids Museum Society
- Construction start
- Jul 20, 2009(actual)
- Construction end
- Sep 9, 2013(actual)
Against the original forecast
- Construction end15 months lateforecast May 31, 2012