Norway House Wastewater Collection and Water Distribution Renewal
Federal contribution
$633,333
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Norway House Community Council
- Construction start
- Apr 26, 2011(actual)
- Construction end
- Nov 14, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 4, 2011
- Construction end7 weeks earlyforecast Dec 31, 2011
Also in Norway House
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32712 in the federal list. How to read these figures.