Provincial Road 373 Grade, Base and Paving (north of PR374 to Sea Falls)
Federal contribution
$8.0M
$8,048,113
Federal share50%
of $16.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Feb 16, 2010(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 5, 2009
- Construction end2 weeks earlyforecast Oct 31, 2011
Also in Norway House
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34692 in the federal list. How to read these figures.