Roadway Work on Route 111
Federal contribution
$1.6M
$1,629,293
Federal share47%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 2, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction end3 months earlyforecast Nov 30, 2010