Construction of a recreational and sports center - Saint-Marc-de-Figuery
Federal contribution
$750,000
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2021
20212022202320242025
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Saint-Marc-de-Figuery
- Construction start
- Mar 25, 2024(actual)
- Construction end
- Jul 15, 2025(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 6, 2024
- Construction end7 months lateforecast Nov 29, 2024