Lepire Street Extension
Federal contribution
$1.6M
$1,632,151
Federal share27%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 10, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Québec
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 21, 2010
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33192 in the federal list. How to read these figures.