Improvements and Expansion of lÉcole de Cirque de Québec
Federal contribution
$1.6M
$1,622,890
Federal share28%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- École de cirque de Québec
- Construction start
- Jul 10, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end4 weeks lateforecast Oct 5, 2011