Road, Sidewalk and Underground Infrastructure Rehabilitation on Principale Street (Highway 173) and du Pont Street (Highway 112)

Vallée-Jonction, Quebec

completeWastewaterISF
Federal contribution
$855,126
Federal share29%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 28, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 2, 2010(actual)
Construction end
Aug 15, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 5, 2010
  • Construction end7 weeks lateforecast Jun 30, 2011

Also in Vallée-Jonction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33236 in the federal list. How to read these figures.