Renewal of water pipes
Federal contribution
$812,831
Federal share36%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20172018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Vallée-Jonction
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Nov 15, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 24, 2017
- Construction end7 months earlyforecast Jun 30, 2019