Back to projects

All season roofed heritage plaque in Baysville

Lake of Bays, Ontario

completeTourismG8LF
Federal contribution
$24,082
Federal share100%

of $24.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.2 years before the announcement.

Program
G8 Legacy Fund
Ultimate recipient
Township of Lake of Bays
Construction start
Jun 25, 2009(actual)
Construction end
Jun 25, 2010(actual)

Also in Lake of Bays

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33326 in the federal list. How to read these figures.