Rehabilitation of the Dwight Community Centre

Lake of Bays, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Lake of Bays
Construction start
Nov 17, 2021(actual)
Construction end
Sep 30, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast May 17, 2021

Also in Lake of Bays

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58799 in the federal list. How to read these figures.