North Arm Territorial Park Picnic Shelter

Behchokö (Rae-Edzo), Northwest Territories

completeRecreationISF
Federal contribution
$100,000
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
2010
Built

Approved 8 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 15, 2009(actual)
Construction end
Jul 30, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2009
  • Construction end2 months earlyforecast Sep 30, 2010