Prelude Lake Territorial Park Shower Building

Yellowknife, Northwest Territories

completeRecreationISF
Federal contribution
$199,929
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
20102011
Built

Approved 8 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 19, 2010(actual)
Construction end
Mar 15, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 11, 2010
  • Construction end2 weeks earlyforecast Mar 31, 2011

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33359 in the federal list. How to read these figures.