Trail Development

Yellowknife, Northwest Territories

completeActive TransportationISF
Federal contribution
$65,000
Federal share50%

of $130.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
2010
Built

Approved 8 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 16, 2009(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2009
  • Construction end4 months lateforecast Jun 30, 2010

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33368 in the federal list. How to read these figures.