Highway 12 from 6 Kilometres North of the Junction of Highway No. 312 to 1 km North of the Waldheim Access
Federal contribution
$1.1M
$1,102,250
Federal share50%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- May 17, 2010(actual)
- Construction end
- Nov 22, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 31, 2010
- Construction end3 months lateforecast Aug 31, 2010
Also in Waldheim
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33381 in the federal list. How to read these figures.