Sidewalks for Waldheim, Saskatchewan
Federal contribution
$149,400
Federal share60%
of $249.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2022
20232024
Built
Approved 5 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Waldheim
- Construction start
- Apr 3, 2023(actual)
- Construction end
- Oct 27, 2024(actual)
Against the original forecast
- Construction start9 months lateforecast Jul 4, 2022
- Construction end2.1 years lateforecast Sep 30, 2022
Also in Waldheim