Goodsoil Wastewater
Federal contribution
$395,702
Federal share29%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
20102011
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Goodsoil
- Construction start
- Aug 12, 2009(actual)
- Construction end
- Sep 24, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 15, 2009
- Construction end5 weeks earlyforecast Oct 31, 2011
Also in Goodsoil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33410 in the federal list. How to read these figures.