Hinterland Road

Goodsoil, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$289,333
Federal share33%

of $868.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 25, 2009
20102011
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Sep 24, 2009(actual)
Construction end
Sep 6, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast May 31, 2009
  • Construction end16 months earlyforecast Dec 31, 2012

Also in Goodsoil

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35980 in the federal list. How to read these figures.