Vanscoy Sewage Lagoon Relocation - Phase 2
Federal contribution
$430,736
Federal share29%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
20102011
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Vanscoy
- Construction start
- Aug 15, 2009(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Jul 31, 2011
Also in Vanscoy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33414 in the federal list. How to read these figures.