Village of Vanscoy - Water Distribution System Upgrades

Vanscoy, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$818,000
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
2021202220232024
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Vanscoy
Construction start
May 16, 2022(actual)
Construction end
Nov 23, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2022
  • Construction end5 weeks earlyforecast Dec 31, 2023