Sachs Harbour Air Terminal Building Replacement

Sachs Harbour, Northwest Territories

completeRegional And Local AirportsISF
Federal contribution
$450,000
Federal share50%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
20102011
Built

Approved 5 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 29, 2010(actual)
Construction end
Oct 29, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Oct 7, 2010