New Diesel Power Plant Construction in Sachs Harbour
Sachs Harbour, Northwest Territories
Federal contribution
$7.5M
$7,481,250
Federal share75%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 4, 2019
201920202021202220232024
Built
Approved 3 months before the announcement.
- Program
- Arctic Energy Fund
- Ultimate recipient
- Northwest Territories Power Corporation (NTPC)
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Mar 29, 2024(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2021
- Construction end7 months lateforecast Aug 31, 2023
Also in Sachs Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52953 in the federal list. How to read these figures.