Interval House - Transforming Spaces

Toronto, Ontario

completeAffordable And Temporary HousingISF
Federal contribution
$250,000
Federal share33%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Interval House
Construction start
Jun 2, 2010(actual)
Construction end
Apr 15, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 13, 2010
  • Construction end2 weeks lateforecast Mar 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33653 in the federal list. How to read these figures.