Scarborough Aboriginal Family-Life Centre

Toronto, Ontario

completeOtherISF
Federal contribution
$845,180
Federal share21%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
May 5, 2010(actual)
Construction end
Sep 23, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 15, 2009
  • Construction end5 weeks earlyforecast Oct 31, 2011

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33752 in the federal list. How to read these figures.