Gentian Lane Reconstruction
Federal contribution
$41,382
Federal share50%
of $82.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 13, 2009
ApprovedJan 28, 2010
2010
Built
Approved 9 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Nov 20, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 28, 2009
- Construction end9 months earlyforecast Aug 31, 2010
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34135 in the federal list. How to read these figures.