Collector Road Preservation - 105th Street
Federal contribution
$169,800
Federal share33%
of $509.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Jul 8, 2009(actual)
- Construction end
- Aug 15, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2009
- Construction end7 weeks earlyforecast Sep 30, 2010
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34149 in the federal list. How to read these figures.