Collector Road Preservation - 105th Street

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$169,800
Federal share33%

of $509.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Jul 8, 2009(actual)
Construction end
Aug 15, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2009
  • Construction end7 weeks earlyforecast Sep 30, 2010