Collector Road Preservation - 103rd Street

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$86,800
Federal share33%

of $260.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Jun 1, 2010(actual)
Construction end
Jul 7, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jul 4, 2010
  • Construction end3 months earlyforecast Sep 30, 2010