Braeburn Active Living Centre

Toronto, Ontario

completeRecreationISF
Federal contribution
$250,000
Federal share33%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
201020112012
Built
Program
Infrastructure Stimulus Fund
Construction start
Nov 30, 2010(actual)
Construction end
Dec 15, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 20, 2010
  • Construction end4 weeks lateforecast Nov 15, 2011