Back to projects

Reception Centre Improvement - COSTI Immigrant Services

Toronto, Ontario

completeAffordable And Temporary HousingISF
Federal contribution
$920,159
Federal share31%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
COSTI Immigrant Services
Construction start
Jun 14, 2010(actual)
Construction end
Oct 31, 2011(actual)