Charlottetown Perimeter Highway - Phase 1

Charlottetown, Prince Edward Island

completeHighways and RoadsISF
Federal contribution
$3.8M
$3,750,000
Federal share50%

of $7.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Aug 17, 2009(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 1, 2009