Charlottetown Perimeter Highway - Phase 1
Charlottetown, Prince Edward Island
Federal contribution
$3.8M
$3,750,000
Federal share50%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Aug 17, 2009(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 1, 2009
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34515 in the federal list. How to read these figures.