Back to projects

Enchant Water Distribution System

Taber, Alberta

completeDrinking WaterISF
Federal contribution
$741,195
Federal share23%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipal District of Taber
Construction start
Jul 1, 2010(actual)
Construction end
Sep 13, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 15, 2010
  • Construction end7 weeks earlyforecast Oct 31, 2011

Also in Taber

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34585 in the federal list. How to read these figures.