Back to projects

Trans-Canada Highway Upgrade - Stratford

Stratford, Prince Edward Island

completeHighways and RoadsISF
Federal contribution
$650,000
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 5, 2010(actual)
Construction end
Nov 26, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2010
  • Construction end2 months lateforecast Sep 20, 2010

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34617 in the federal list. How to read these figures.