Westlock Sanitary Main Trunk Sewer
Federal contribution
$851,780
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Westlock
- Construction start
- Jul 15, 2009(actual)
- Construction end
- Aug 23, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 1, 2009
- Construction end2 months earlyforecast Oct 31, 2011
Also in Westlock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34620 in the federal list. How to read these figures.