Town of Westlock - Stormwater Management Facilities
Federal contribution
$1.2M
$1,248,256
Federal share40%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 25, 2020
2021
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Westlock
- Construction start
- Feb 22, 2021(actual)
- Construction end
- Nov 15, 2021(actual)
Against the original forecast
- Construction end14 months earlyforecast Dec 31, 2022