Rebuilding the Querbes Avenue Bridge

Montréal, Quebec

completeHighways and RoadsISF
Federal contribution
$1.8M
$1,800,000
Federal share50%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 1, 2010(actual)
Construction end
Jun 16, 2011(actual)

Against the original forecast

  • Construction end5 months earlyforecast Oct 31, 2011

Also in Montréal