Back to projects

St. John’s Petty Harbour Long Pond Water Treatment

St. John's, Newfoundland and Labrador

completeDrinking WaterISF
Federal contribution
$5.2M
$5,249,157
Federal share14%

of $37.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2009
201020112012201320142015
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of St. John's
Construction start
Jun 22, 2009(actual)
Construction end
Jul 31, 2015(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2009
  • Construction end16 months lateforecast Mar 31, 2014

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34706 in the federal list. How to read these figures.