Richmond - Lansdowne Road Extension

Richmond, British Columbia

completeHighways and RoadsISF
Federal contribution
$647,181
Federal share32%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Richmond
Construction start
Jul 31, 2009(actual)
Construction end
Jan 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2009
  • Construction end8 weeks earlyforecast Mar 31, 2010

Also in Richmond

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34845 in the federal list. How to read these figures.