Highway 3 - Replacement of Cedar Creek bridges #1 and #2

Hope, British Columbia

completeHighways and RoadsISF
Federal contribution
$2.7M
$2,683,961
Federal share50%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 4, 2009(actual)
Construction end
Jun 15, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2009
  • Construction end7 weeks earlyforecast Jul 31, 2011