Highway 3 - Replacement of Cedar Creek bridges #1 and #2
Federal contribution
$2.7M
$2,683,961
Federal share50%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2009
- Construction end7 weeks earlyforecast Jul 31, 2011
Also in Hope
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34858 in the federal list. How to read these figures.