Peters First Nation - Fraser River Flood Control Berm

Hope, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$4.9M
$4,939,598
Federal share100%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2022
20222023
Built

Approved 16 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Peters First Nation
Construction start
Jan 17, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Nov 22, 2021
  • Construction end3 months lateforecast Dec 31, 2022